Install Crew requirements
- Two Dollies
- Genie Lift
- Cleaning Solution – 10/90 (10% isopropyl alcohol / 90% distilled
water solution)
- Cleanroom towels
- Electric drill with Phillips bit
- 9/16" ratchet / wrench
- ½" ratchet / wrench
- Touch-up paint
- Pigtail adapter may be required for power
Installation sequence:
1. Lift unit up into the air with secure lifting device. Note:
do not damage HEPA filter during lift, ensure forks or lifting device
protrude through both ends.
- Holds legs upright and align with slots on far ends.
Lower unit onto legs and bolt with 3/8’ bolts.
- Gasket top of back panel and screw in self-tapping screws.
Ensure that top of back panel is flush with back flange of unit.
- Gasket aluminum angle frame of Plexiglas and screw onto sides
of unit.